v0.8.0 (draft, stacked on #7): risk events, uncertainty classes, sensitivity, progress updates, leveling, DCMA options - #8

Merged
cruiseliner merged 2 commits into
mainfrom
feature/risk-events-progress-leveling
Oct 17, 2026
Merged

cruiseliner merged 2 commits into
mainfrom
feature/risk-events-progress-leveling

Conversation

@cruiseliner

Copy link
Copy Markdown
Owner

Stacked on #7 (base: feature/calendars-holidays-risk). Review and merge #7 first; this PR will then retarget to main.

v0.8.0

  • Risk events (risk --risks raid.csv: id, name, probability, min/likely/max impact days, linked task rows). A common-cause event adds one sampled impact to every linked task in the same run. The report shows each event's hit rate and mean finish impact.
  • Uncertainty classes: an uncertainty CSV column (labor, equipment, design, vendor, permit, weather, fixed), with --class name=o,p overrides. O/P columns still win. The built-in factors are documented as planning defaults to calibrate, not as statistics.
  • Sensitivity: Pearson correlation of each task's duration with the finish, shown as a tornado list in the text output and as sensitivity in JSON.
  • Progress updates: --progress progress.csv --status-date D on from-csv, cpm and risk.
    • Columns: actual start/finish, remaining days, % complete.
    • Remaining work is scheduled after the status date.
    • The XML carries actuals, % complete and the status date.
    • Imported .mpp/.xer files bring their own progress and status date.
  • Leveling within float: from-csv --level / cpm --level, a serial leveler (1 unit per resource). Delayed tasks get an SNET constraint and a note; conflicts it can't resolve are reported.
  • DCMA: check --exclude-endpoints (Primavera P6 support (XER + P6 XML), v0.2.0 #1 ignores the start/finish milestones) and check --thresholds key=value,….
  • XER writer: not in this PR, documented as next on the roadmap.

Tests

  • fmt, clippy -D warnings and cargo test all pass: 38 unit, 18 cli, 8 p6, 14 reports and 1 doc test.
  • risk over 783 corpus files: 582 OK, 0 panics. The 201 errors are expected: 197 have no tasks, 3 are password-protected and 1 needs the de locale.

Known gaps

  • No general correlation matrix, only common-cause events.
  • The leveler is not Project's or P6's leveling (no partial units, splitting or priorities).
  • risk ignores --level.
  • Progress uses date-granular actuals.

@cruiseliner
cruiseliner changed the base branch from feature/calendars-holidays-risk to main October 17, 2026 00:31
@cruiseliner
cruiseliner marked this pull request as ready for review October 17, 2026 00:31
@cruiseliner
cruiseliner merged commit 2bfd04d into main Oct 17, 2026
5 checks passed
@cruiseliner
cruiseliner deleted the feature/risk-events-progress-leveling branch October 17, 2026 00:50
Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment

Labels

None yet

Projects

None yet

Development

Successfully merging this pull request may close these issues.

1 participant